A takes 6 days to complete a work and B takes
10 days to complete the same work. They work
together for 2 days and then B leaves. How much
more time will A require to complete the work?
Answers
Answered by
0
Answer:
A work in one day is 1/6
B work in one day is 1/10
both work in one day is 1/6 + 1/10 = 16/60
they complete work in two days is 2*(16/60) = 16/30
work remaining is 1 - 16/30 = 14/30
A complete 14/60 work in (14/30)*6 = 14/5
so A takes 2.8 days more to complete remaining work.