A takes 6days less than B by to finish a piece of work. if both A and B together can finish the work in 4 days. find the time taken by B along the to finish the work.
Answers
Answered by
6
Answer:
time taken alone by B = 12 Days
Step-by-step explanation:
Let us assume b takes alone x days
Then A takes x-6 days
1/4 = 1/x + 1/(x-6)
solving we get
x² - 14x + 24 = 0
(x-12)(x-2) = 0
x = 12 as x can not be 2 because then Number of Days for A will be -ve (2-6 = -4 )
amitnrw:
Please mark the answer as "The Brainliest answer" if it helps