A takes 8 days to finish a piece of work. B takes 10 days to finish the same work. How long will it take to finish the work when both of them are working together?​

Answers

Answered by pathakrakesh121
1

I think 2 days

Step-by-step explanation:

hope it will correct make me brainlist please

Answered by akshat5926
2

Answer:

40/9

Step-by-step explanation:

Time by A = 8 days

Time by B = 10 days

Work done by A in 1 day = 1/8

Work done by B in 1 day = 1/10

Work done by both in 1 day = 1/8 + 1/10

                                              =  9/40

Thus days needed to finish the work = 40/9 days