Math, asked by gurjotmanpreet0, 3 days ago

A takes 8 days to finish a piece of work. B takes 10 days to finish the same work. How long will it take to finish the work when both of them are working together? O 18 days
2 days
9days
40/9days​

Answers

Answered by udgirkar67
1

Answer:

Given:

A alone can complete the work in = 8 days

B alone can complete the work in = 10 days

Formula:

Total work = Efficiency x Time

X

Calculation:

Total work = 40 unit

→ Efficiency of A = 5 units/day

Efficiency of B = 4 units/day

Total efficiency of A and B = 5 + 4 = 9 units

..A and B together can complete the work = 40/9

= 4 days

(LCM of 8, 10)

Step-by-step explanation:

please mark me as brainiests and follow me i will also mark you as brainiests and I will follow you