A takes 8 more days than B to finish a work. A and B start this work and B leaves the work 9 days before the work is finished if A complete 75%of the work. how long would. A have taken to finish the work alone.
Answers
A & B together can complete work in (25x20)/(25+20) =500/45 = 100/9 days.
They complete 5 x 9/100= 9/20 work in 5 days.
Remaining 11/20 work done by B in 11/20 x 20 = 11 days.
A will take 14 days to finish the work alone.
Step-by-step explanation:
Let the time taken by B working alone = x days,
So, time taken by A working alone = (x + 8) days
∵ A complete 75% of the work,
So, the day he will work = 75% of (x+8) = = ,
⇒ B has to complete 25% of work,
That is, days he will work = 25% of x = = ,
Since, B leaves the work 9 days before the work is finished,
Days for which A worked - Days for which B worked = 9 days.
Now, x + 8 = 6 + 8 = 14
Hence, time taken by A to finish the work alone would be 14 days.
#Learn more :
A take 10 days less than time taken by b to finish a piece of work. if a and b together can finish the work in 12 days find the time taken by b to finish the work
https://brainly.in/question/4568569