Math, asked by radha5266, 10 months ago

A takes 8 more days than B to finish a work. A and B start this work and B leaves the work 9 days before the work is finished if A complete 75%of the work. how long would. A have taken to finish the work alone.​

Answers

Answered by HeAvEnPrlnCesS
2

A & B together can complete work in (25x20)/(25+20) =500/45 = 100/9 days.

They complete 5 x 9/100= 9/20 work in 5 days.

Remaining 11/20 work done by B in 11/20 x 20 = 11 days.

Answered by slicergiza
15

A will take 14 days to finish the work alone.​

Step-by-step explanation:

Let the time taken by B working alone = x days,

So, time taken by A working alone = (x + 8) days

∵ A complete 75% of the work,

So, the day he will work = 75% of (x+8) = \frac{75(x+8)}{100} = \frac{3(x+8)}{4},

⇒ B has to complete 25% of work,

That is, days he will work = 25% of x = \frac{25x}{100} =  \frac{x}{4},

Since, B leaves the work 9 days before the work is finished,

Days for which A worked - Days for which B worked = 9 days.

\frac{3(x+8)}{4}-\frac{x}{4}=9

\frac{3x+24-x}{4}=9

\frac{2x+24}{4}=9

2x+24=36

2x=12

\implies x = 6

Now, x + 8 = 6 + 8 = 14

Hence, time taken by A to finish the work alone would be 14 days.

#Learn more :

A take 10 days less than time taken by b to finish a piece of work. if a and b together can finish the work in 12 days find the time taken by b to finish the work

https://brainly.in/question/4568569

Similar questions