A takes five days less than B in digging a field .if A and B together work they take 6 days .in how many days A and B work
Answers
Answered by
0
Answer:
A would take 10 days and B would take 15 days.
Step-by-step explanation:
Let A take x days.
B would take (x+5) days.
A.T.Q,
(1/x)+(1/x+5)=1/6
Solving this ,we get
x = 10
A takes 10 days an B takes 15 days