Math, asked by joytwenty12, 1 year ago

A takes twice as much as B and thrice as much as C to finish a work; working together they can finish the work in 10 days. Find the time each will take to finish the work separately.

Answers

Answered by debtwenty12pe7hvl
1

The working capacity of B = 2 times the working capacity of A

B = 2 A

The working capacity of C= 2 times the working capacity of A

C = 3 A

Now, A + B+ C can finish 1 work 10 days

A + 2A+ 3A can finish 1 work 10 days

6 A can finish 1 work in 10 days

A cando 1work in 60 days

B can do 1 work in 12

time taken by A = 12*60 = 30 days

C can do 1 work in13timetakenbyA=13∗60=20days  ANS