A takes twice as much time as B and C together take to finish the job. A and B working together finish the job in 4 days. C alone can do the same job in 4 days. In how many days can B alone do the same job?
Answers
Answered by
0
Answer:
6 days
Step-by-step explanation:
Let the number of days taken by B to finish the work be x
Then, in 1 day he finishes 1/x part of the work
According to the question, A takes twice as much time as B = 2(x) = 2x
Then, in 1 day A can finish 1/2x part of the work.
A and B working together can finish the work in 4 days.
so, in one day, A and B working together can finish 1/4 part of the work.
1/x+1/2x = 1/4
2+1/2x = 1/4 (2x is common)
3/2x = 1/4
2x = 4*3 (by cross multiplication)
2x = 12
x = 12/2 = 6.
so B takes 6 days to complete the full work, A takes 12 days and C takes 4 days to complete.
Similar questions
Hindi,
2 months ago
Math,
2 months ago
India Languages,
2 months ago
Accountancy,
5 months ago
Math,
10 months ago
English,
10 months ago
Math,
10 months ago