A takes x hours to complete a task. B takes 5 more hours than A. If they work together, they can complete the task in 6 hours. Find the value of x.
Answers
Answered by
8
Let A alone take X hours
Then X takes (X+5) hours
Together in 1 hour they finish 1/X + 1/(X+5) of the work
Since together they take 6 hours, in 1 hour they finish 1/6 of the work
- (X-10) ( X+3) =0
- X = 10 hours
ANSWER A alone takes 10 hours and B takes 15 hours