Math, asked by aryanyadav09, 1 year ago

A tash is completed by 25 person in 9 days if they work 6 hours perday . How many days will be needed to complete the task if 15 person work for 9 hours everyday​

Answers

Answered by MavisRee
7

Answer:

10 days are required to finish the work if 15 person work for 9 hours everyday

Step-by-step explanation:

Given that 25 persons can complete work in 9 days is they work 6 hours per day

25 persons working for 6 hours means

25 \times 6 = 150\hspace{0.1cm}person-hours\hspace{0.1cm}per\hspace{0.1cm}day

Then, 25 persons work for 9 days means

 150 \times 9 = 1350\hspace{0.1cm}person-hours

Thus, total work =\hspace{0.1cm}1350\hspace{0.1cm}person-hours

Now, let x days are required to finish the work if 15 person work for 9 hours everyday

Thus,

Total\hspace{0.1cm}work\hspace{0.1cm}=15 \times x \times 9\hspace{0.1cm}person-hours\\\\135x = 1350\\\\x=\frac{1350}{135}=10\hspace{0.1cm}days

Hence, 10 days are required to finish the work if 15 person work for 9 hours everyday

Answered by Namratabagde561
0

Answer:

that is right solution

Step-by-step explanation:

please mark s follo me