A tash is completed by 25 person in 9 days if they work 6 hours perday . How many days will be needed to complete the task if 15 person work for 9 hours everyday
Answers
Answered by
7
Answer:
10 days are required to finish the work if 15 person work for 9 hours everyday
Step-by-step explanation:
Given that 25 persons can complete work in 9 days is they work 6 hours per day
25 persons working for 6 hours means
Then, 25 persons work for 9 days means
Thus, total work
Now, let days are required to finish the work if 15 person work for 9 hours everyday
Thus,
Hence, 10 days are required to finish the work if 15 person work for 9 hours everyday