A task is completed by 15 men in 16 days . how many men will be needed to complete 1/14th of the task in 15 days .
Answers
Answered by
3
Answer:
Simple way to understand this question is to go step by step
10 men requires 14 days to finish a work so in one day they finishes 1/14th of total work
Now 10 men can finish 1/14 th of total work in one day so 1 man can complete 1/140 th of total work
Work is to be completed in 4 days so total work completed by 1 man in 4 days would be 4*(1/140) i.e 1/35
1 man completed 1/35th of work in 4 days hence 35 men would be required to make it complete i.e 35*(1/35) = 1
So 25 more men required
Same steps can be followed for similar questions