A task is completed by 30 persons in 15 days if they work 6 hours per day. How many hours of work will be needed every day if 20 persons have to complete it in 15 days.​

Answers

Answered by prasanthikuchipudi
3

Answer:

9 hrs

Step-by-step explanation:

we know,

work=men*hours*days

A task is completed by 30 persons in 15 days if they work 6 hours per day.

work=30*15*6    ----(1)

How many hours of work will be needed every day if 20 persons have to complete it in 15 days.​

let x be hours

work=x*20*15   ----(2)

Eq (1)=(2)

30*15*6=x*20*15

x=9 hrs