A person wanted to complete a work
in 40 days and employed 100 men
for the job. After 20 days only 40% of
the work was completed and so he
employed 75 more women to assist
the men. If a man does as much
work as 3 women, find the total time
required to complete the job? (Time
and work II).
Select one:
a. 24 days
b. 44 days
c. 40 days
d. 20 days