A time study was carried out for a machining operation. A qualified operator was selected for the time study. The details of observed times are as under s no part of operation observed time (seconds) 1 2 3 1 loading 10 9 11 2 machining 55 48 41 3 unloading 10 12 8 the worker rating was 105. Relaxation allowance for this operation as found out from the table for a male worker is 10%. A contingency time of 4% is required in the process. Calculate standard time. What should be the target production of a shift of 8 hours
Answers
Answered by
3
Answer:
the time study. The details of observed times are as under s no part of operation observed time (seconds) 1 2 3 1 loading 10 9 11 2 machining 55 48 41 3 unloading 10 12 8 the worker rating was 105. Relaxation allowance for this operation as found out from the table for a male worker is 10%. A contingency time of 4% is required
Answered by
6
Relaxation allowance for this operation as found out from the table for a male worker is 10%. A contingency time of 4% is required in the process production of a shift of 8 hours
Similar questions
History,
6 months ago
Math,
6 months ago
Math,
1 year ago
Environmental Sciences,
1 year ago
Computer Science,
1 year ago