A total of 280 workers were deployed to unload the ship’s cargo within 10 days.
After a 3 day, only ¼ of all the items were removed. So how many more workers were hired
To complete the work on time????
Answers
Answered by
0
Answer:
Step by step explanation-
To finish a work in 3 days 250 labourers are required
To finish it in 7 days ( more time) less labourers required
Multiplying fraction is 3/7(less)
To finish 1/4 work 250 labourers are required
To finish 3/4 work ( more work) more labourers are required.
Multiplying fraction is (3/4)/(1/4) ( more)
Answer=250×3/7×3/4×4/1=250×9/7=2250/7=321.4~321 labourers.
Final answer=321–250=71 more labourers required.