A toy company requires 36 machines to produce car toys in 54 days. How
many
machines would be required to produce the same number of car toys in 81 days?
Answers
Answered by
100
Step-by-step explanation:
36machines-54days
x-81days
36×81÷54
=54machines
Answered by
2
Answer:
hello plz follow me plz mark as brainlist
Step-by-step explanation:
54 machines