a typist had to type 360 pages for a project. typing daily 4 pages more than it was planned, the work was completed one day ahead of the schedule. for how many days did she work on the job?
Answers
Answered by
1
❗❗❗❗HEYA❗❗❗❗
✈✈✈✈✈✈✈✈✈✈✈✈✈✈✈✈✈✈✈✈
❤❤❤❤❤❤❤❤❤❤❤❤❤❤❤❤❤
◆◆◆◆◆◆◆◆◆◆◆◆◆◆◆◆◆
⏩ANSWER & EXPLANATION ✏
pages= 360
daily work= 4 pages
day's need to complete the project are =
: . 360÷4= 90 days
◆◆◆◆◆◆◆◆◆◆◆◆◆◆◆◆◆
⚡⚡⚡⚡⚡⚡⚡⚡⚡⚡⚡⚡⚡⚡
❤❤⭐⭐@NR⭐⭐❤❤
❤❤HOPE IT HELPS YOU❤❤
Answered by
1
Answer:10 days
Step-by-step explanation:
let typist type x pages daily and completed project in y days
then 360/x=y ------eq 1
and 360/(x+4)=y-1
⇒360//(x+4)+1=y
put y value in eq 1
⇒360/x=360/(x+4)+1
⇒1440=x²+4x
⇒x=36
and y=10
she did completed her job in 10 days