A und B can do a job in 25 days. After 15 days of working together. B leaves. A completes the remaining part of the job in 20 days, how long would each take to complet the job working separately?
Answers
Answered by
0
Step-by-step explanation:
let total work =25
{A+B} efficiency =1
after 15 days,
15×1 =15
remaining work =10
A efficiency = 10/20
= 1/2
B efficiency =1-1/2
= 1/2
A take = 25×2= 50days
B take = 25×2 =50 days