A verandah is 40m long and 15m broad. It is to be paved with stones, each measuring 6dm by 5dm. Find the number of stones required.
Answers
Answered by
749
since:
l =40m
b=15 m
area of verandah[rectangle]=l*b
=40m*15m
=600m.sq
and stone each measuring 6dm by5dm
by converting it into meter we get,
0.6m by 0.5m
now, area of stone= l*b
=0.6m*0.5m
=0.3m.sq
now, number of stone required =area of verandah/area of stone
=600m.sq/0.3m.sq
=600*10/3
=6000/3
=2000.
done! may you got use of this ....
l =40m
b=15 m
area of verandah[rectangle]=l*b
=40m*15m
=600m.sq
and stone each measuring 6dm by5dm
by converting it into meter we get,
0.6m by 0.5m
now, area of stone= l*b
=0.6m*0.5m
=0.3m.sq
now, number of stone required =area of verandah/area of stone
=600m.sq/0.3m.sq
=600*10/3
=6000/3
=2000.
done! may you got use of this ....
Answered by
184
Answer:
2000
Step-by-step explanation:
1 m = 10 dm
Length of verandah = 40 m = 400 dm
Breadth of verandah = 15 m = 150 dm
So, Area of verandah =
=
=
Length of stone = 6 dm
Breadth of stone = 5 dm
So, Area of 1 stone =
=
=
So, Number of stones required =
=
Hence 2000 stones are required .