a WBS does not help in
1.functional sizing
2.identifying task listing
3.clarrifying in scope vs out of scope
4.identifying resource for various deliverables.
please answer fast
Answers
Answered by
2
Answer:
Option 3
clarrifying in scope vs out of scope
Explanation:
WBS Is Not a Plan or Schedule
The WBS cannot be used as a replacement for the project plan or schedule. A WBS is not required to be created in any type of order or sequence. It is simply a visual breakdown of deliverables.
Answered by
2
Answer:
✌❤✨_ I HOPE HELP YOU _✨❤✌
ANSWER = OPTION C
❤✨_ TAKE CARE & BE HAPPY _✨❤