Math, asked by adhnannishadp, 10 months ago

A work can be completed by 6 men in 90 days. How many men are required to finish the same work in 36 days?

Answers

Answered by BrainlyRaaz
37

Given :

  • A work can be completed by 6 men in 90 days.

To find :

  • No. of men are required to finish the same work in 36 days =?

Step-by-step explanation :

A work can be completed by 6 men = 90 days.

A work can be completed by 1 men = 90 × 6 days.

Now,

No. of men are required to finish the same work in 36 days,

= (90 × 6)/36

= 540/36

= 15

Therefore, No. of men are required to finish the same work in 36 days = 15 men.

Answered by Anonymous
8

Given :-

  • Work completed by 6 men in 90 days

To find :-

  • Men required to complete the same work in 36 days = ?

Solution :-

Men required to complete the work in 90 days are :- 6

Men required to complete the work in 1 day :- 6/90

Men required to complete the work in 36 days :- ( 6/90 ) × 36

= 36 / 15

= 12 / 5

Answer :- 12/5 men are required .

• ) Your question is not properly correct . I hope the numbers given by you are not proper .

•) Since , 12/5 such no. of men does not exsist