Math, asked by sachinarora2918, 1 year ago

A work can be completed by p and q in 12 days, q and r in 15 days, r and p in 20 days. In how many days p alone can finish the work?

Answers

Answered by dwipendukundu210
0
Your questions is:-
A work can be completed by p and q in 12 days, q and r in 15 days, r and p in 20 days. In how many days p alone can finish the work?
Answer:-
p alone can finish the work in 30days
Attachments:
Similar questions