中 A work can be finished in 14 days by 36 workers. If the work were to be finished in & days. How additional workers would many be required?

Answers

Answered by CuriousRose
0

Answer:

In 14 days a piece of work can be done by = 36 workers

In 1 day the same work can be done by=36×14 workers

In 8 days the same work can be done by =36×14/8 = 63 workers

Number of extra workers = 63–36 = 27 workers.

Therefore, 27 more workers are required to finish the same work in 8 days.