A work can done by A and B in 10 days,
B and C in 5 days, C and A in 30 days
then in how many days can A, B and C
together finish the work ?
(1) 3 Days (2) 6 Days
(3) 8 Days (4) 5 Days
Answers
Answered by
2
1/5+1/10+1/30
6+3+1/30
10/30
10/30*2
so andwer is. 6 days
shivamani72:
thank you
Answered by
1
A,B,C take 8 days to finish work together