A work can finish 6 male workers or 9 female workers in 20 days take finish the same work with 4 male workers and 4 female workers? please this time work equation format solution explain ?
Answers
Answered by
7
I assume you want to find how many days will it take to finish the work if 4 male and 4 female workers work together....
Attachments:
Nithin438:
15 is wrong ans, optional answer is =18 days.