Math, asked by bhoomika4511, 9 months ago

a work is completed by 10 men in 50 days how long will 25 men take to complete the work ​

Answers

Answered by qamar24567890
9

Answer:

Step-by-step explanation:

10 MEN = 50 DAYS

25 MEN = X DAYS

IF 10 MEN TAKES 50 DAYS TO WORK

25 MEN WILL TAKE 10 DAYS TO COMPLETE THE WORK.........

THANKS

PLZ MARK ME AS BRAINLIEST......!!!

THANK & FOLLOW ME....!!!

Answered by NavWade
8

Answer:

20 days

Step-by-step explanation:

                    No. of men                     No. of days taken to complete the work

                         10                                                        50

                         25                                                         x

10/25 = x/50 ( Inverse variation)

25*x = 10*50

x = 500/25

x = 20

∴ 25 men will take 20 days to complete the work.

Hope this helps!!