A work is completed by 15 men in 30 days.in how many days can 12 men complete the work given the time spent is decreased by 1/4th the previous time??
Answers
Answered by
2
Answer:
24 days are required.
Step-by-step explanation:
GIVEN:
15 Men finish's work by 30 days
TO PROVE:
How many days 12 men can do the work?
First:
Find how much days One person need ?
30÷15=2
So,each men need 2 days to finish work.
Days required for 12 men to finish work is=
12×2=24 days
Hence, 24 days are required to finish work by 12 men .