A work is completed by 15 men in 30 days. In how many days can 12 men complete the work given that the time spent per day is increased by 1/4th the previous time?
Answers
Answered by
3
Answer:
each men need 2 days to finish work. Hence, 24 days are required to finish work by 12 men.