a work is to be finished in 12 days by 20 workers. after 8 days, it is found tat only 1/2 part of the work has been done . how many more workers should now be engaged in order to finish the job in time
Answers
Answer:
A works twice as fast as B. They work together and complete a job in 8 days. How long would A take to complete the job?
What are the documents needed for opening new SBI account?
Any Individual who desires to open savings bank account in individual capacity need to furnish following documents:- 1. Permanent
Let us assume A’s effort for the work is x (per day) ,
As, A works twice as fast as B, so, B’s effort for the work is 0.5x (per day)
Thus , in a day both A & B spend 1.5x amount of effort.
They complete the task in 8 days, tat means the total amount of effort spend by both working together is 1.5x*8 = 12x
By this we can conclude that this job need 12x amount of effort to be completed
As, a provides x amount of effort per day, it will require 12 days to complete the job.
Thanks
Step-by-step explanation: