a work twice as fast as B and C work thrice as fast as a if all of them work simultaneously they complete the work in 18 days find the time taken by C alone to complete the work
Answers
Answered by
0
Answer:
ridoudhddhdkoseugedbxjsoisgddg
Answered by
0
Step-by-step explanation:
From Given facts
If X is the work done by B, then work done by A is 2X
Irrespective of duration Total work is X+2X = 3X
ie B did 1/3 of work in 24 days and A did 2/3 of work in 24 days
since B finished only 1/3 work in 24 days , to complete the full work by him alone is 24/ 1/3 = 24* 3= 72 days