A work twice or fast as B. if both of them together finish a work in 12 days. how much time shall A take to do it?
ranjan143nyk:
hiii @anjali
Answers
Answered by
0
Answer:
18 days
Step-by-step explanation:
Answered by
1
Answer:
Let:
A completes the work in 'x' days.
B will complete the work in '2x' days.
Now:
In 1 day, work done by A = 1/x
In 1 day, work done by B = 1/2x
A.T.Q.
1/x + 1/2x = 1/12
( 2 + 1)/2x = 1/12
3/x = 1/6
x = 3 × 6
x = 18
Hence:
A will take 18 days to complete his work.