A workforce of 210 men with a contractor can finish a work in 16 months. How many niore
be employed so that the work is completed in 14 months?
Answers
Answered by
18
People required for 16 months = 210 men
For, 1 month = 210 * 16
Calculating,
For , 14 months, 3360/14=240
Hence,
More, Men required=240-210
=> 30