A works twice as fast as B and B works twice as fast as C. All three working together can complete a work in 4 days with the help of D. If D alone can complete this work in 16 days, then in how many days will A complete 75% of the work alone?
Answers
Answered by
2
Answer:
Right Answer is: C
A alone can complete the 75% of the total work in = 28/4 = 7 days.
Step-by-step explanation:
Hope it helped you.
Answered by
43
A works twice as fast as B and B works twice as fast as C
- Let efficiency of C = 1 m
- Efficiency of B = 2 m
- Efficiency of A = 4 m
Given that D alone can finish the same task in 16 days.
As total work is 100%
So work done by D in 4 days = 25%
It is also given that all three working together can finish total task in 4 days with the help of D
So work done by (A+B+C) in 4 days = 100% - 25% = 75%
Efficiency of (A+B+C) = 1+2+4 = 7 m
So work done by (A+B+C) in 4 days = 7×4 m
Now we will find that in how many days will A alone finish 75% of the same task.
Efficiency of A = 4 units
Let A will finish 75% of the same task in x days.
Similar questions