A works twice as fast as B and B works twice as fast as C. If A and B together complete a
work in 4 days, then C alone can complete the work in
(A) 8
(B) 6
(C) 24
(D) 12
Answers
Answered by
1
Step-by-step explanation:
Answer
Ratio of rates of working of A and B = 2 : 1.
So, ratio of times taken = 1 : 2.
B's 1 day's work =
12
1
∴A's one day's work=
6
1
(2 times the work of B)
(A+B)'s one day's work=
6
1
+
12
1
=
12
3
=
4
1
So,A and B together can finish the work in 4 days.