A works twice as fast as B. If B can complete
a piece of works independently in 12 days, then
the number of days taken by A and B toget
together to finish the work.
Answers
Answer:
A and B together can finish the work in 4 days.
Step-by-step explanation:
Ratio of rates of working of A and B = 2 : 1.
So, ratio of times taken = 1 : 2
B's 1 day's work = 1/12
∴A's one day's work= 1/6 (2 times the work of B)
(A+B)'s one day's work= 1/6+ 1/12 = 1/4
Therefore, A and B together can finish the work in 4 days.
Question understanding :-
• Here, It is mentioned in the question that there are two people one is denoted by A and Other is denoted by B .
• Now, It is mentioned that A is working twice faster than B
• Here, It is also mentioned that B complete his work in 12 days
Now, We have to find that in how many days they both complete the work if they work together ?
Given :-
• A work twice as fast as B
• B can complete a piece of work independently in 12 days
Solution :-
Here, A is twice faster than B
The ratio of rates of working A and B
= 2 : 1
So ,
Time ratio of B = 1/12
Therefore,
Time ratio of A will be = 2/12 = 1 / 6
Here,
We find that if B will finish his work in 12 days so A will finish it in 6 days
According to the question,
If ( A + B) working together .
Then,
(A + B ) ratio of rates of working
= 1 / 6 + 1/ 12
= 2+ 1/12
= 3/12
= 4