A works twice as fast as B.If B can complete a work in 18 days independently,the number of days in which A and B can together finish the work is:
A) 4 days
B) 6 days
C) 8 days
D) 10 days
Answers
Answered by
1
Answer:
the answer is C
Step-by-step explanation:
if A works twice as fast as B that means it would take him 9 days to complete the job