Math, asked by lokhimondal, 1 year ago

A works twice as fast as B if both of them can together finish a piece of work in 12 days then B alone can do it in

Answers

Answered by ayushanand8947
46
Hey Dear,
Your Answer is Here !!
Let A completes the work in X days .

Then according to question, B completes the same work in 2X days.

Now let us formulate this.

1/A + 1/B = 1/8 ……(Given)

1/X + 1/2X = 1/8

Taking LCM

2/2X + 1/2X = 1/8

3/2X = 1/8

2X/3 = 8

2X = 24

X = 12

So A will complete the work alone in 12 Days.

✓ Follow me !
✓ Hope It Help's
✓ Thank You !


sss177: mr. u asked my hair ugly
sss177: wht did u think u are
sss177: listen u are super duper ugly
Answered by yamunaramhzb
22

Answer:

Step-by-step explanation: The answer will be 36 days but I don't know the steps at all.