Aakash can do a piece of work in 20 days and his friend Rohit in 25 days they work together for 10 days and then Akash left away in how many days will Rohit complete the remaining work
Answers
Answered by
7
Answer:
Hi
Happy Republic Day
Do you remember me.
How are you??
tiwariabhimanyu88:
who are you
Answered by
6
Answer:
2.5 days
Step-by-step explanation:
Work done by Aakash in one day=1/20
Work done by Rohit in one day=1/25
Work done by both of them in one day= 1/20+1/25= 9/100
Work done by both in 10 days= 9/100×10=9/10
Work that Rohit has to do alone= 1/10
Work done by Rohit in one day-----1/25
Work done by Rohit in x days-----1/10
By cross multiplication, x/25=1/10
x/5=1/2
x=5/2= 2.5 days
Therefore, Rohit takes 2days and 12 hours to finish the work