Abhilasha begins working on a task and continues working on it for 18 days, finishing 80% of the assigned labour. She employs Dhriti to assist her with the project. They labour together for another 18 days, and the project is completed. What is the difference between Abhilasha and Dhriti in terms of efficiency
hello
every one
Kaise ho sab!
Aaj main apne projects mein busy thi to morning mein online nahi aa payi
but finally my work is completed
Abhilasha begins working on a task and continues working on it for 18 days, finishing 80% of the assigned labour. She employs Dhriti to assist her with the project. They labour together for another 18 days, and the project is completed. What is the difference between Abhilasha and Dhriti in terms of efficiency
Answers
Answered by
1
Hey! I'm fine nd u?
Nice your project completed^_^
I have lots of works pending to do: -(
Similar questions
CBSE BOARD X,
17 hours ago
Environmental Sciences,
17 hours ago
History,
17 hours ago
English,
1 day ago
Science,
8 months ago
Geography,
8 months ago
Math,
8 months ago