Abhishek can do a piece of work in 40 days. He alone worked at it for 8 days and then Bacchhan completed alone the rest work in 24 days. In how many days they will complete the whole work, working together?​

Answers

Answered by nirmitmenghani
3

Answer:

17 and 1/7 days

Step-by-step explanation:

No. of days Abhishek took to complete the work = 40 days.

His 1 day work = 1/40

therefore, work done by him in 8 days = 1/40 * 8

= 8/40 = 1/5.

Work left = 1 - 1/5

               = 4/5        

No. of days Bacchan took to complete the rest of the work = 24 days.

His 1 day work = 4/5 / 24

= 1/30

1 day work of both = 1/30 + 1/40

= 7/120

No. of days took by both to complete the work =  1/  7/120

= 17 and 1/7 days.