Math, asked by prasath201198, 6 hours ago

Abinaya can be do 1/5 of the work in 20days while Bhadrinath can do 20% of the work in 30 days. How long will it take for both of them to complete the work?

Answers

Answered by rahulmi
2

Answer:

60 days

Step-by-step explanation:

Abinaya can do in 1 day = 1/(5*20) = 1/100 part

Bhadrinath's can do in 1 day = 1/(30*5) = 1/150 part

both can do in 1 day = Abinaya's 1 day + Bhadrinath's 1 day =1/100+1/150

=(6+4)/600= 10/600=1/60 part

time to complete the work by both = 1/(1/60) = 60 days