Explanation:
The Budhi Gandaki Hydroelectric Project is a proposed hydroelectric power plant in Nepal, to be developed by Nepal Electricity Authority. This storage hydropower plant is to be located on the Budhi Gandaki River, approximately 2 km upstream of its confluence with Trishuli River, about 55 km west of Kathmandu
Explanation:
The Budhi Gandaki Hydroelectric Project is a proposed hydroelectric power plant in Nepal, to be developed by Nepal Electricity Authority. This storage hydropower plant is to be located on the Budhi Gandaki River, approximately 2 km upstream of its confluence with Trishuli River, about 55 km west of Kathmandu.
Spillway capacity: 12,827 m3/s
Construction cost: 250 crores USD
Impound: Budhi Gandaki River
Total capacity: 3,3 km3
Installed capacity: 1,200 MW
Catchment area: 5.000 km²
Surface area: 49.8 km²