Acan do a piece of work in 10 days and B can do it in 15 days they worked together for 5 days the rest of the work is finished by C in 2 days if they get rupees 900 for the whole work how should advise the money and what are their daily wages
Answers
Answered by
1
Answer:
Work done by A and B in 5- days =5/10+5/15= 25/30= 5/6.
The remaining (1–5/6)= 1/6 - part of the work is done by C- in 2-days.
So C- can complete in day = 1/(2 X6)=1/12- part of the work. The whole work can be completed by C in-12– days.
Therefore the efficiency ratio of A:B:C =1/10: 1/15: 1/12
= 6 :4 : 5
So wage of A= ₹ 1500 x 5/10= ₹ 750
Daily wage of A=₹ 750/5= ₹150
Wage of B=₹ 1500 x 5/15= ₹ 500
Daily wage of B=₹ 500/5= ₹100
Wage of C=₹ 1500 x 1/6= ₹ 250
Daily wage of C= ₹ 250/2= ₹ 125
Therefore the sum the daily of wages of B and C =(₹100+125) = ₹ 225.