Actual production on
particular day is 120 units,
time allowed for 10 units is
1 hour and hourly rate is
Rs.4. Earning under piece
rate system?
Rs. 32
Rs. 40
Rs. 48
Rs. 45
Submit
Answers
Answered by
5
Answer:
rs.40 is the answer ok na
Answered by
2
Earning under piece rate system is Rs. 48/-
Actual production on particular day is = 120 units
Time allowed for 10 units is = 1 hr
By applying unitary method, we get,
Time allowed for 1 unit is = 1/10 hr
So, time allowed for 120 units = 120/10 hr
= 12 hr
So, there is actually 12 hr of production hours per a day.
Now, hourly rate is = Rs. 4/-
So, the total rate for 12 hr is = (12×4) = Rs. 48/-
So, earning under piece rate system is Rs. 48/-