Math, asked by ram9055, 11 months ago

actually number of men needed​

Attachments:

Answers

Answered by Bhaskarnath
1
14 men needed

hope it helps

follow

ram9055: How
Answered by neerajmahato1086
2

Answer:

Step-by-step explanation:No of days needed to complete the work =5

No of people required = let be x

It is given that 10men can do the half work in 7 days

So simply we get that 14 men will be needed to complete the work in 5 days

Hope it will help

Thanks for asking