Adish, Anubhav and Akanksha can finish a work
independently in 10,12 and 15 days. Akanksha
started the work and after 1 day, Anubhav joined
her. After 1 day of Anubhav, Adish also joined
them but left 3 days before completion of the work.
Find the total number of days taken to complete
the work ?
Answers
Answered by
0
Answer:
9days they take to finish