Math, asked by Ashishkumar9990, 10 months ago

After working for 8 days, Arun finds that only 13 rd of the work has been done. He employs Akhil who is 60% as efficient as Arun. How many days more would Akhil take to complete the work?

A) 24.5 days B) 26.6 days C) 25 days D) 20 days

Answers

Answered by sudiptamaji2007
1

16Q:

After working for 8 days, Arun finds that only 13 rd of the work has been done. He employs Akhil who is 60% as efficient as Arun. How many days more would Akhil take to complete the work?

A) 24.5 days

B) 26.6 days

C) 25 days

D) 20 days

Answer: B) 26.6 days

Explanation:

Arun has completed 13rd of the work in 8 days

Then he can complete the total work in

13 ---- 8

1 ---- ?

= 24 days

But given Akhil is only 60% as efficient as Arun

Akhil =124×60100=140

Akhil can complete the total work in 40 days

Now, remaining 2/3rd of work can be completed in

1 ------ 40

23 ------ ?

= 26.66 days.