Math, asked by manojchowdary443, 7 months ago

aight objective type questions :
A can do a work in 12 days and B can finish the same work in 24 days. If they work togeth
many days will they complete the work ?
d) 6
c) 9
a) 10
b) 8​

Answers

Answered by Anonymous
8

Answer:

Let their be 24 units of work (LCM of 12&24).

A does 24/12= 2 units work per day.

B does 24/24= 1 unit work we day.

Both do (2+1)=3 units work per day.

Number of days to complete the total work i.e. 24 units of work =24/3 = 8 days

Ans: 8 days