Ajay and Deep together can complete a piece of work in 12 days. If Ajay alone can complete the same work in 30 days. Days in which Deep alone can complete that work is, *
Answers
Answered by
0
Answer:
Total days to complete by both of them=
1÷(1/12+1/3)
= 1÷(1+4)/12= 1÷5/12.
1*12/5= 2 2/5 days
Step-by-step explanation:
please mark me brainlist thank you and the explanation is in the answer