Math, asked by sourabhdeka123, 5 months ago

Aland B can do a work in 12 days and 24
days respectively. They worked together for
4 days, but after 4 days B left. How long will
it be taken by A to complete the remaining work? plz step by step​

Answers

Answered by basharathussain189
0

Answer:

A in one day complete 1/12 of the work

B in one day complete 1/24 of the work

Together A and B in one day 1/8 of the work

In 4 days A and B completed 1/8 × 4 = 1/2 of the work

A will in one day do 1/12 of the work

Remaining 1/2 of the work to be completed by A

A will take 6 days to complete the work

Answer:- 6 days.

Similar questions